ISO 9001:2015 Verified
DIPLOMA
LANGUAGE ACADEMY
DIPLOMA
LANGUAGE ACADEMY
DIPLOMA
LANGUAGE ACADEMY
You may be busy in your jobs, learning or family lives and can't get around to preparing and takes the certificate exams but on the other side you urgently need some useful AD0-E903 certificates to improve your abilities in some areas. If you choose the test AD0-E903 certification and then buy our AD0-E903 prep material you will get the panacea to both get the useful AD0-E903 certificate and spend little time. Passing the AD0-E903 test certification can help you stand out in your colleagues and have a bright future in your career.
The customization feature of these Adobe Workfront Project Manager Professional (AD0-E903) practice questions (desktop or web-based) allows users to change the settings of their mock exams as per their preferences. Customers of Prep4sures can attempt multiple AD0-E903 Exam Questions till their satisfaction. On each attempt, our AD0-E903 practice exam will give your results on the spot.
>> Adobe AD0-E903 Valid Test Simulator <<
You will get a lot of personal and professional benefits after passing the Adobe AD0-E903 test. The Adobe AD0-E903 exam is a valuable credential that will assist you to advance your career. The Adobe AD0-E903 is a way to increase your knowledge and skills. You can also trust on Prep4sures and start Adobe Workfront Project Manager Professional AD0-E903 test preparation with Adobe AD0-E903 practice test material.
Topic | Details |
---|---|
Topic 1 |
|
Topic 2 |
|
Topic 3 |
|
NEW QUESTION # 60
The second task in a project should be completed within 48 hours and needs to begin 5 business days after the first task is completed.
Which task settings should be configured to meet these requirements?
Answer: C
Explanation:
In Adobe Workfront, to configure tasks according to the requirement of the second task beginning 5 business days after the first task, you need to set the appropriate "Duration" and use "Finish-Start" dependencies. The task's duration is key to determining the time allowed for its completion. The "Finish-Start" dependency ensures that the second task begins only after the first is finished, and a lag can be set to introduce a delay, such as 5 business days. Setting a "Finish-Start" dependency with a lag allows for proper scheduling of tasks in sequence without overlapping.
NEW QUESTION # 61
A project manager is assigned to a new Workfront request. The request specifies that the management team's sign-off is needed before the project can begin.
What is the appropriate action for the project manager to take?
Answer: B
Explanation:
In Workfront, approval processes are designed to handle scenarios where certain team members must give formal approval before work can proceed. In this case, the project manager should set up a customized approval process that routes the request through the necessary stakeholders (management team) for their sign-off. This ensures proper governance and tracking.
NEW QUESTION # 62
What occurs when an individual enters a new commit date that is after the original planned date of a task?
Answer: A
Explanation:
When a user updates the Commit Date to a date later than the original planned date in Adobe Workfront, the Planned Completion Date of the task is automatically updated to reflect the new commit date. This feature ensures that the timeline is adjusted based on the most current commitment by the task assignee, which can then impact downstream tasks and the overall project schedule.
This change streamlines project planning and helps keep task dependencies aligned with realistic completion expectations.
NEW QUESTION # 63
A creative team accesses their assigned work in a My Tasks list report. The team would like to easily see any New tasks highlighted for visibility. How can the project manager accommodate the team's request?
Answer: C
Explanation:
To meet the team's request for highlighting new tasks, the most effective solution is to create a View that uses Column Rules. These rules allow for conditional formatting based on task criteria, such as highlighting new tasks in a specific color for easy identification. This approach enhances visibility without requiring the creation of filters or new reports, and it makes it easier for users to see relevant tasks within their existing task lists.
NEW QUESTION # 64
A team lead needs to regularly report on the adherence of budget and timeline of a group of projects.
What should the team lead use to organize these projects to allow them to be tracked together?
Answer: A
Explanation:
In Workfront, a "Program" is used to group related projects that share a common objective or need to be tracked together, such as adherence to budget and timeline. Programs allow for collective reporting on these projects, making it easier for team leads to monitor progress, manage resources, and report on key performance indicators (KPIs) across multiple projects.